Lamma Island cement plant jetty: pile wrapping and fenders
Removing and refitting the pile wrapping and fender frames along a dolphin jetty, completed in 16 days.
- Year
- 2019
- Location
- Lamma Island
- Status
- Completed
- Category
- Underwater & marine
The cement plant jetty on Lamma Island is a line of dolphins on raked piles, E to M, spaced 6.1, 19.65, 9.25, 9.25 and 27.25 m apart and joined by truss walkways, with deck levels from +1.0 to +5.0 mPD.
The work was to take off and refit the pile wrapping and three types of fender frame, built from 102 × 50 mm channel and 50 × 50 and 25 × 25 mm angle, between +0.55 and +1.6 mPD. It ran from 8 to 23 February 2019, 16 days in all.