Kei's
© Yan & Partners, 2026
EnTc
Home / Projects

Projects

Completed works, ongoing projects and concepts, from 1999 to today. Projects marked “Founder's project experience” are ones our founder worked on as part of another company's team, not under the Yan & Partners name.

2024
2024 · Drainage & MDP

Thin-layer green roofs with MDP

Thin-layer green roofs drained by MDP, collecting rainwater for reuse.

View project →
2022
2022 · Underwater & marine · Founder's project experience

Island Eastern Corridor pile cap repair

Working platforms and access cages for repairing defective pile caps under the Island Eastern Corridor.

View project →
2022 · Underwater & marine

Lung Kwu Chau: uncovering a buried outfall diffuser at −22 mPD

A daily diving plan to find and clear a buried seabed diffuser near a busy fairway, 6–8 nautical miles from the typhoon shelter.

View project →
2020
2020 – 2022 · Hydraulic

Kai Tak River: riverbed inspection, drain seals and diversion screens

Three years of diving work in the Kai Tak River for the Central Kowloon Route: a CCTV survey of the riverbed, steel seal plates for live drains, and underwater diversion screens around the new bridge platform.

View project →
2020 – 2021 · Hydraulic

Box culvert desilting, Hoi Fai Road to Olympian City

Diver-operated desilting of a flooded box culvert, with on-site settling and dewatering so only dry spoil leaves the site.

View project →
2020 · Underwater & marine · Method design (tender stage)

Pui O sewage outfall: diffuser installation method

A nine-step method, prepared at tender stage, for installing a diffuser on the Pui O outfall inside a sheet-pile cofferdam built from a temporary jetty.

View project →
2020 · Temporary works · Method design (tender stage)

Third Runway: pile-cap cofferdam and watertight formwork

A temporary-works scheme for casting marine pile caps at the Third Runway: a sheet-pile cofferdam, a steel trestle and a 62-tonne watertight formwork lowered over each pile group.

View project →
2019
2019 – 2022 · Hydraulic

Exhibition Station: sealing and reopening drains in a live culvert

Confined-space diving on the Shatin to Central Link at Exhibition Station: surveying a flooded box culvert, sealing branch drains from Ø900 to Ø2,100 mm, and later removing the temporary bulkheads.

View project →
2019 · Temporary works

To Kwa Wan – Kai Tak: steel walers for a tunnel cofferdam

Steel waler and strut frames to brace the sheet-pile walls of a tunnel cofferdam, drawn in 3D for fabrication.

View project →
2019 · Underwater & marine

Lamma Island cement plant jetty: pile wrapping and fenders

Removing and refitting the pile wrapping and fender frames along a dolphin jetty, completed in 16 days.

View project →
2018
2018 – 2019 · Underwater & marine · Founder's project experience

Avenue of Stars: removing old marine piles

Underwater cutting and removal of the old marine piles beneath the Avenue of Stars for its expansion.

View project →
2018 · Underwater & marine · Founder's project experience

Causeway Bay seawater pump house intake

Underwater inspection and construction at the seawater intake of a building's cooling-water pump house.

View project →
2016
2016 · Temporary works

Tseung Kwan O: sheet-pile bulkhead and silt-curtain frame

A steel frame for driving a sheet-pile bulkhead and holding a silt curtain, plus a water-stop gate for the drain behind it.

View project →
2014
2014 · Hydraulic

Tai Po Water Treatment Works: pumping sand from a deep culvert

Divers working from a man-cage at the bottom of a 2 m caisson removed 50–70 m³ of sand from a water culvert with a 3-inch sand pump.

View project →
2013
2013 · Hydraulic

Stonecutters Island sewage culvert: stop-gate bulkhead

A diver-installed steel stop-gate built up in sections inside a live sewage culvert, after a CCTV and measurement survey.

View project →
2013 · Underwater & marine

Stanley: encasing a sewage outfall pipe on rock

A Ø450 mm outfall crossing a rocky foreshore was encased in concrete using steel formwork, sandbags and mortar bags.

View project →
2012
2012 – · Drainage & MDP

Multipurpose Drain Pipe (MDP)

Our patented drainage and filtration pipe that resists clogging. Silver Award, HKMA/HKT Global Innovation Award 2024/25.

View project →
2012 · Underwater & marine

Tseung Kwan O submarine cable: relocating the beach manhole

Moving the beach manhole where an international submarine cable comes ashore, using precast units, underwater pipework and grout placed from a floating platform.

View project →
2012 · Underwater & marine

Lamma Power Station jetty: working platforms and lifting frames

Temporary working platforms hung from the jetty piles, a platform for the fender dolphins and a vertical lifting frame for repair works at the Lamma Power Station jetty.

View project →
2012 · Underwater & marine

Submarine gas main: free-span inspection and support

Underwater inspection of a section of submarine gas pipeline left spanning over a scoured seabed, and a plan to support it and fill the scour with aggregate.

View project →
2012 – · Temporary works

Temporary works design

Access towers, floating rafts and platforms we design so crews can work safely over and in water.

View project →
2012 · Underwater & marine

Chung Hom Kok: landing a new submarine cable

The shore end of a new cable at Chung Hom Kok: a 3 m trench through armour rock, an HDPE duct set in concrete, and a sea earth jetted into the seabed.

View project →
2012 · 2016 · Underwater & marine

Diving 40 m down a flooded caisson shaft

Confined-space diving inside a Ø2,000 mm steel caisson about 40 m below ground: clearing sediment and cutting out the reinforcement underwater.

View project →
2012 · Underwater & marine

Airport artificial island: removing an abandoned telephone cable

Divers searched for an old submarine telephone cable buried up to 5 m deep, uncovered it by airlift and recovered it by winch before reclamation.

View project →
2011
2011 · Underwater & marine

North Point: removing old dolphins beside the Island Eastern Corridor

Old concrete dolphins on bored piles were lifted out by crane barge after divers cut each pile 500 mm below the seabed.

View project →
2010
2010 · 2016 – 2017 · Underwater & marine

Wan Chai Reclamation Phase 1 & 3

Seawall blocks and caissons for Section C2 (2010); temporary diversion pipes, cooling-water outfall works, stop gates and grouting for Section C3 (2016–2017).

View project →
2010 – 2011 · Underwater & marine

Cross-harbour water main, West Kowloon to Sai Ying Pun: the landing

Underwater temporary works where a new cross-harbour water main comes ashore: cofferdam bracing to −15.7 mPD, pile cutting below the seabed, and a dry welding caisson at −17 mPD.

View project →
2010 · Underwater & marine

Xiamen–Kinmen fibre cable: burial to 3 m

Two diver teams trenched either side of a 32 mm submarine fibre cable so it lowered itself to 3 m below the seabed, checked every 10 m.

View project →
2010 · Hydraulic

Seawater pump houses: installing trash screens

Divers set 11–16 m wide screen frames against the seawall at three seawater pump houses, drilling and welding underwater to close every gap.

View project →
2010 – 2011 · Hydraulic

Sai Ying Pun box culvert: bulkhead, joint sealing and grouting

A six-step method to isolate a seawall box culvert, clear it and seal its joints, with the bulkhead lowered at night by divers working inside.

View project →
2010 · 2022 · Underwater & marine

Tuen Mun Area 38: finding and protecting outfall diffusers

Airlift searches for buried outfall diffuser heads, then extending and protecting the risers with rockfill and cement sandbags.

View project →
2010 – 2011 · Underwater & marine

Shitai 158: patching a sunken cargo ship

Divers on mixed gas mapped and patched six breaches in a sunken cargo ship's hull, then a refloating plan was drawn for a grounded vessel.

View project →
2010 · Underwater & marine

Ninepin Group: lifting a fishing-vessel wreck from −31 m

Divers rigged slings around a sunken fishing vessel at −31 m so a derrick barge could right it and lift it.

View project →
2009
2009 · Underwater & marine · Founder's project experience

Tong Fuk sea earth cables, Lantau

Laying and burying sea earth cables for the Tong Fuk international telecommunications station.

View project →
2009 – 2010 · Hydraulic

Tsuen Wan stormwater culverts: guide rails and stop gates

Removable steel stop gates on guide rails at the upstream and downstream ends of two stormwater culverts, installed by divers in about five days.

View project →
2009 – 2010 · Underwater & marine

Black Point Power Station: clearing the cooling-water intake heads

Three dive teams located the offshore intake heads of Black Point Power Station, opened them, cleared the screens and airlifted silt from the pits.

View project →
2009 · Underwater & marine

Guangdong–Hainan 500 kV interconnector: protecting the submarine cables

Burying and protecting the 500 kV cables that link Hainan to the mainland grid: jetting them into the seabed at Xuwen, cutting through volcanic rock, and covering them with concrete slabs or grout bags at −35 m off Haikou.

View project →
2009 – 2010 · Underwater & marine

AAG submarine cable: burying an in-service cable 5 m deep at −33 m

Divers airlifted a trench beneath a live Asia-America Gateway cable at −33 mPD, letting it sink 5 m into the seabed to −38 mPD.

View project →
2009 · Underwater & marine

SkyPier, Hong Kong International Airport: pontoon moorings

Setting typhoon sinkers of up to 68 tonnes and installing the elastic mooring system for the landing pontoons at the airport's ferry pier.

View project →
2009 · Underwater & marine

Kowloon Park swimming pool: refloating a sunken floor panel

A movable pool-floor panel sank to the bottom of the pool. Divers raised it evenly using inflatable hoses and floats.

View project →
2009 · Underwater & marine

Zhuhai: pulling a 550 m cable-duct bundle under a river

A 550 m bundle of seven HDPE ducts, ballasted with concrete weights, was pulled across a riverbed through steel sleeves in the levees and jetted in.

View project →
2009 · Hydraulic

Peng Chau submarine pump station: condition survey

A diver survey of an offshore pump station built from four precast rings, gridded like a clock face so every defect could be located.

View project →
2009 · Hydraulic

Cheung Chau–Lantau water main: finding a leaking joint

A diver inspection of the flanged joint between the steel and fibreglass sections of a submarine water main at −11 PD.

View project →
2007
2007 · Underwater & marine

Discovery Bay shipyard slipway repair

Underwater repair of worn lifting-platform rails and a seabed depth survey for desilting at the Discovery Bay shipyard.

View project →
2007 – 2012 · Underwater & marine

Castle Peak Power Station: sealing cooling-water culverts

Five years of diving work inside the cooling-water culverts of Castle Peak Power Station: sealing leaking joints with stainless plates, clearing intake screens and repairing a joint on the seabed within a 24-hour shutdown.

View project →
2005
2005 · Underwater & marine

Stanley Pier reconstruction

Underwater welding, pile works and floating steel formwork for rebuilding a pier in open water, planned over 190 working days.

View project →
2001
2001 · 2012 · Underwater & marine

Ocean Terminal, Tsim Sha Tsui: seawall survey and repair

An underwater survey of the blockwork seawall from the Star Ferry to the China Ferry section, and repairs to voids and displaced blocks under the car park and pump houses.

View project →
2001 – 2020 · Underwater & marine

Caltex Tsing Yi Terminal: twenty years of jetty maintenance

Recurring work at an oil terminal: inspection scaffolds for the pier piles, new rubber fenders, seawall grout bags and a full mooring-buoy package.

View project →
2001 · Underwater & marine

Guishan Island, Zhuhai: a blockwork unloading jetty

Design of a gravity jetty built from precast concrete blocks, stacked in eight courses from −12 to +7.5 PD on a graded rock foundation.

View project →
2001 – 2010 · Research

Our own cable and pipe burial machines

Design drawings for a jet sled that buries submarine cables up to 3.5 m deep and a trencher for 700 mm pipelines.

View project →
More projects
Underwater & marine · Founder's project experience

Quarry Bay sunken vessel: survey and salvage

Underwater survey of a sunken barge, then cutting it into three sections of 91, 119 and 180 tonnes to lift it out.

View project →
Underwater & marine

Tseung Kwan O: raising a sunken hopper barge

A step-by-step salvage plan for a sunken split-hopper barge, lifted with a derrick barge and moved to shallow water.

View project →
Hydraulic

Fleming Road culvert: floating in a seal plate

A culvert survey every 40 m and a method for floating a 500 kg seal plate into a flooded culvert and fitting it by hand.

View project →
Temporary works

Tseung Kwan O – Lam Tin Tunnel: concreting formwork platforms

Suspended formwork platforms for placing concrete around marine piles on the tunnel project.

View project →
Research

Improved underwater welding handle

Our handle design is now the standard across Hong Kong's commercial diving industry.

View project →