© Yan & Partners, 2026
EnTc
Underwater & marine

Tseung Kwan O submarine cable: relocating the beach manhole

Moving the beach manhole where an international submarine cable comes ashore, using precast units, underwater pipework and grout placed from a floating platform.

Year
2012
Client
NEC
Location
Tseung Kwan O, New Territories
Status
Completed
Category
Underwater & marine

Where a submarine cable comes ashore it runs into a beach manhole, half in and half out of the sea. At Tseung Kwan O the manhole had to be moved, which meant building a new one in the tidal zone.

Five stages

  1. Remove the armour rock and excavate.
  2. Level the bed and place precast units of 9 and 13 tonnes.
  3. Install galvanised-iron cable pipes underwater.
  4. Fix steel formwork.
  5. Grout with concrete pumped from a truck on shore through pipes laid across a floating platform.

A silt curtain on floating buoys, weighted with geotextile, kept sediment inside the works area. We also prepared the hoarding design report for the shore side.

Drawings

Beach manhole, construction stages · 海灘人井施工步驟
Beach manhole, construction stages · 海灘人井施工步驟
Beach manhole design · 海灘人井設計
Beach manhole design · 海灘人井設計
Works area and hoarding · 施工範圍及圍欄
Works area and hoarding · 施工範圍及圍欄
Relocation set-out · 改位座標
Relocation set-out · 改位座標