Cross-harbour water main, West Kowloon to Sai Ying Pun: the landing

Underwater temporary works where a new cross-harbour water main comes ashore: cofferdam bracing to −15.7 mPD, pile cutting below the seabed, and a dry welding caisson at −17 mPD.

Year
2010 – 2011
Client
Penta-Ocean Construction
Location
West Kowloon seawall
Status
Completed
Category
Underwater & marine

Where a submarine water main meets the seawall, the pipe has to be pulled up a slope, guided into position and welded to the land section. At West Kowloon all of that happened underwater.

  • Cofferdam bracing. Divers installed the walings and struts of the sheet-pile and pipe-pile cofferdam, from +1.9 down to −15.7 mPD, using steel sections from 305 × 305 × 97 to 356 × 406 × 393 UC, with guide plates, welded brackets and bolted joints.
  • Pile cutting. Around each old pile, silt was airlifted from −20.0 to −21.4 mPD, about 9 m³ per pile, so divers could cut the pile 500 mm below the seabed.
  • Dry welding caisson. A caisson with a turning roller sat at −17 mPD. It guided the head of the pulled pipe, was sealed around it and pumped dry, so the landing joint could be welded in the dry.
  • Turning shaft. The roller shaft had its own installation, temporary attachment and removal procedures.

We also designed a debris screen gate for the works and ran CCTV along the seawall joints.

Drawings

Pipe pulled down the slope into the landing caisson · 水管沿斜坡拉入登陸沉箱
Pipe pulled down the slope into the landing caisson · 水管沿斜坡拉入登陸沉箱
Turning shaft and caisson sections · 轉軸及沉箱剖面
Turning shaft and caisson sections · 轉軸及沉箱剖面