SkyPier, Hong Kong International Airport: pontoon moorings
Setting typhoon sinkers of up to 68 tonnes and installing the elastic mooring system for the landing pontoons at the airport's ferry pier.
- Year
- 2009
- Client
- Gammon Construction
- Location
- SkyPier, Chek Lap Kok
- Status
- Completed
- Category
- Underwater & marine
SkyPier's landing pontoons have to stay put through typhoons while ferries berth against them every day. We set up landing pontoons No.1 and No.2 in a 12-step sequence:
- Lay the typhoon sinkers of 21, 42, 67.5 and 68 tonnes from an 80-tonne derrick lighter.
- Lay the sinkers for the elastic Seaflex mooring units.
- Straighten the typhoon sinker chains.
- Install the Seaflex units.
- Moor and fix each pontoon.
Each step was planned in working days, from 2 to 18, and some lifts were done overnight to keep the pier running. A dredger, derrick lighters and underwater marker buoys were used throughout.