Kei's
© Yan & Partners, 2026
EnTc
Underwater & marine

Stanley Pier reconstruction

Underwater welding, pile works and floating steel formwork for rebuilding a pier in open water, planned over 190 working days.

Year
2005
Location
Stanley, Hong Kong Island
Status
Completed
Category
Underwater & marine

Rebuilding a pier over open water means working below the tide line. We planned the whole job around a set of reusable waterproof steel formworks that are floated into position, sunk around each pair of piles to form a watertight mould for the concrete.

Sequenced in five stages

  • Day 30: underwater welding of I-beam ties between piles, removal of nine platform piles, a crane platform, and the first formworks at A7/F7 and A6/F6 with five cross beams. A7/F7 concreted.
  • Day 60: five more platform piles removed and the platform partly rebuilt, formworks moved to A5/F5 and A4/F4, four precast beams installed, A6–A5 concreted.
  • Day 90: formworks at A3/F3, four more precast beams, A4/F4 concreted.
  • Day 120: the A4/F4 formwork modified for A2/F2, formworks at A1–A2, precast stair beams.
  • Day 190: the last precast units at A1–A3, final concrete pours, formworks and pile ties removed, and the upper-deck working platform built.

Formwork designed to float

Each formwork unit was drawn with its own weight and buoyancy so it could be towed and placed without heavy lifting: the A3/F3 unit weighs 4.8 t with 28 t of buoyancy, A7/F7 7.5 t with 58.5 t, and the larger A5–A4 unit 14 t with 127 t. A temporary working platform was added in December 2005.

From the drawings

The pile caps and beams were cast below water inside watertight steel formwork boxes (PB1–PB7, A1–A7 and F1–F7), built from 5–6 mm plate on channel frames with marine-glue seals. A full set weighs about 14 tonnes against 127 tonnes of buoyancy; the smaller set 7.5 tonnes against 58.5 tonnes. A temporary working platform carried the work, and the programme ran in stages over about 190 days: precast beams in, formwork fitted and stripped, concrete poured, pile ties welded underwater, platform piles removed. The same formwork was later adapted for Wong Shek Pier (2007).

Drawings

3D overview · 立體圖
3D overview · 立體圖
3D: formwork placement · 鐵模安裝
3D: formwork placement · 鐵模安裝
3D: stairs and deck · 梯級及樓面
3D: stairs and deck · 梯級及樓面
3D: completed structure · 完成結構
3D: completed structure · 完成結構
3D: pile layout · 樁位
3D: pile layout · 樁位
3D: temporary works · 臨時工程
3D: temporary works · 臨時工程
Elevation · 立面圖
Elevation · 立面圖
Stage 1, day 30 · 30天進度
Stage 1, day 30 · 30天進度
Stage 2, day 60 · 60天進度
Stage 2, day 60 · 60天進度
Stage 3, day 90 · 90天進度
Stage 3, day 90 · 90天進度
Stage 4, day 120 · 120天進度
Stage 4, day 120 · 120天進度
Stage 5, day 190 · 190天進度
Stage 5, day 190 · 190天進度
Formwork A3/F3 · 鐵模
Formwork A3/F3 · 鐵模
Formwork A7/F7 · 鐵模
Formwork A7/F7 · 鐵模
Formwork A5–A4 · 鐵模
Formwork A5–A4 · 鐵模
Formwork A6/F6 · 鐵模
Formwork A6/F6 · 鐵模
Temporary platform, plan · 臨時工作台平面
Temporary platform, plan · 臨時工作台平面
Temporary platform, elevations · 臨時工作台立面
Temporary platform, elevations · 臨時工作台立面
Temporary working platform and formwork layout · 臨時工作台及防水模佈置
Temporary working platform and formwork layout · 臨時工作台及防水模佈置